We can even schedule a lot of new construction progresses at the calendar week 35.
For example the strip foundations for the office- and social buildings have been finished and the storage building has been removed until only the frame construction was left. Also the 65 fountain fundaments for the production building are already concreted and the first bucket fundaments have been delivered and moved into their right position.