The first interior traffic routes are getting built with a lean concrete which provides the basis for a subsequent asphalting.
Furthermore a transformer for the 1000 KVA electric power supply has been arranged and the shelf mounting in the storage building has begun. But there was recently also the kick-off for the installation of the first pulley blocks in the production hall.